Tamboran Resources has completed stimulation, clean-out and completion activities of the Shenandoah South 3H, 4H and 5H wells in the Northern Pilot Area of the Beetaloo Basin in Australia, it said in a statement on Monday.
The stimulation work was carried out by Liberty Energy (LBRT) and the program was the first three-well zipper stimulation and largest campaign to date in the Beetaloo Basin, with 178 phases over 30,000 feet in the Mid Velkerri B shale formation.
The stimulation program completed an average of 6.7 stimulated stages each day, with pumping operations of more than 20 hours per day and 12 stages delivered in a single day.
Tamboran successfully placed the first Beetaloo Red locally produced sand in 10 stages across a lateral section in the SS-4H well, using tracers to evaluate stage performance.
The wells will be tied to the Sturt Plateau Compression Facility (SPCF) where construction is near complete.
The complete is within its A$141 million budget ($97 million) and first gas sales, to the Northern Territory Government, are scheduled for Q3.
Tamboran has also started drilling the SS-7H, 8H and 9H wells with the Helmerich & Payne (HP) rig on the SS1 well pad. All three wells will be stimulated in H2 and tied to the SPCF when needed.