FINWIRES · TerminalLIVE
FINWIRES

Noble Sees Contract Resequencing Shift Rig Activity as Dayrates Remain Firm, TPH Says

By

Noble (NE) lowered its fiscal 2026 adjusted EBITDA outlook after contract resequencing offset otherwise resilient offshore drilling activity, TPH Energy Research said in a Tuesday note.

Two Petrobras (PBR) floaters reduced Q2 revenue by about $43 million, although adjusted EBITDA still broadly matched TPH's expectations despite the lost contract revenue.

Management attributed the weaker outlook to revised schedules for the Noble Viking, Noble Intrepid and Noble Innovator, rather than non-productive time, according to TPH Energy Research in a Tuesday note.

The Noble Viking will complete its firm contract in October 2026 in Southeast Asia and could remain idle before customers exercise its remaining two contract options, according to the research firm.

BP (BP) transferred the remaining backlog from the Noble Innovator to the Noble Intrepid, freeing the Innovator in September 2026 while extending the Intrepid's contract through September 2027.

Four optional wells for the Northern Endurance Partnership could keep the jackup active through most of 2028, TPH said.

Noble also moved the Noble Developer's expected contract completion to January 2027 from the prior August 2027 schedule, which had included a five-well option. TPH said the revised timeline likely reflects the customer's plan to retender future Gulf of America drilling work.

Floater operating days came in about 2% below TPH's expectations, while average floater dayrates met estimates at about $413,000.

Jackup dayrates reached $197,000, above TPH's $179,000 estimate, while reimbursable revenue totaled about $40 million versus TPH's $35 million forecast.

Noble also retired the Ocean Apex ahead of TPH's expected 2027 timeline. Management added that tightening market conditions have pushed leading-edge rates for Tier I ultra-deepwater drillships into the mid-$400,000s, TPH said.

Adjusted EBITDA totaled $212 million, compared with TPH's $210 million estimate and the Street's $219 million forecast.

The company lowered its fiscal 2026 adjusted EBITDA guidance to $850 million to $925 million from $940 million to $1.02 billion, reducing the midpoint by about $93 million, TPH said.

Noble maintained its fiscal 2026 capital expenditure guidance at $615 million to $665 million, in line with TPH's $639 million estimate.

Second-quarter capital expenditures reached about $205 million, above the Street's $159 million forecast and TPH's $135 million estimate, resulting in negative free cash flow of $59 million versus the Street's negative $9 million forecast and TPH's positive $53 million estimate.

Price: $39.29, Change: $-3.82, Percent Change: -8.86%

Related Articles

Commodities

Australian, Western Australian Governments Launch AU$4 Million Pre-feasibility Study for Building New Oil Refinery

The governments of Australia and Western Australia will conduct a jointly funded AU$4 million pre-feasibility study for a new large-scale oil refinery in the state, to be built by Perdaman, according to a Tuesday statement.The proposed refinery is expected to create thousands of jobs, boost the local economy, and help secure diesel for regional communities in Western Australia.This is the first agreement to be signed as part of the Australian government's AU$10 million support for feasibility studies into furthering fuel refining capabilities, as it seeks to retain current refining capability in the decade beyond 2030, per the statement.Australia currently has two oil refineries: in Brisbane, Queensland and in Geelong, Victoria.

ASX 200
Commodities

Moody's Raises JSW Steel Issuer Rating to Baa3, Assigns Stable Outlook

Moody's Ratings upgraded JSW Steel's (BOM:500228, NSE:JSWSTEEL) long-term issuer rating to Baa3 from Ba1 and assigned a stable outlook, according to a Monday press release.The ratings agency cited the company's stronger credit profile following debt reduction and its position as India's largest steel producer with cost-competitive operations.The ratings agency also upgraded JSW Steel's senior unsecured ratings to Baa3 from Ba1 and withdrew its Ba1 corporate family rating.Moody's expects JSW Steel's debt-to-EBITDA ratio to improve to 2.0x to 2.5x over the next 12 to 18 months from 3.4x in fiscal 2025-26, supported by debt repayment using proceeds from the sale of a 50% stake in Bhushan Power & Steel.The agency said the stable outlook reflects expectations that the company will continue to grow earnings while maintaining financial discipline as it expands capacity to meet rising steel demand in India.

BOM:500228NSE:JSWSTEEL
Commodities

PJM Board Orders Reliability Measures as Power Demand Accelerates

PJM will file two proposals with the Federal Energy Regulatory Commission as it expects large electricity loads to increase by 70 gigawatts by 2038, the grid operator said Monday.The proposals would establish a Reliability Backstop Procurement to attract new generation and an Interim Resource Adequacy Service to support large load growth while protecting reliability during periods of capacity shortages.PJM expects new large loads to increase by 70 GW by 2038, while 15 GW of generation has retired since 2022. The 2028/2029 capacity auction also ended 6,831 megawatts below the system's reliability requirement for the grid serving 67 million people.The board said the region needs additional power supplies without placing unnecessary cost burdens on consumers."The present trajectory of rapid load growth, tightening supply and rising capacity costs is not sustainable," the board said, adding that the "region needs substantial new investment in supply, and the central affordability question is how the costs of that investment should be allocated."PJM launched a bilateral contracting process with a June 9 request for proposals and expects the first buyer-seller matches in August. The process will continue into early next year and reduce the amount of new generation PJM needs to procure.The grid operator plans a one-time Reliability Backstop Procurement from Sept. 30 through Oct. 21, with results expected in early December.Winning projects can secure commitments of up to 15 years, while accepted offers will face a $555/MW-day cost cap, according to PJM.Eligible resources include new generation that adds new installed capacity and maximum facility output, qualifying Capacity Interconnection Rights created or transferred from units deactivated after April 10, 2026, and resources that failed to secure commitments in the 2028/2029 auction.The proposal also covers new annual demand response and distributed energy resources, provided aggregators demonstrate qualifying sites and contracts for the full 15-year commitment. Eligible projects must begin operating by June 1, 2032.Resource developers will pay for transmission network upgrades and include those costs in their offers.PJM will allocate procurement costs to Load Serving Entities in affected areas, while state regulators will determine how those costs apply across customer classes.The board also instructed PJM to exclude incremental new large loads from future Reliability Pricing Model auctions beginning with the 2029/2030 delivery year.The move aims to prevent existing customers from absorbing higher capacity costs created by new demand.PJM will create a Large Load Registry for customers with at least 50 MW of peak demand at one site or connected sites within a one-mile radius. The registry will improve load forecasts and transparency while protecting confidential information.Under the proposed Interim Resource Adequacy Service, new large loads without dedicated generation by June 1, 2027, or other secured supply will reduce demand before broader emergency load management measures begin during capacity shortages.PJM said the proposed cost allocation framework follows Ratepayer Protection principles supported by data centers, the White House and PJM governors.The board added that states will play a key role in assigning retail costs because PJM cannot allocate them directly to individual data centers.