Oriole Hydro Padas, a subsidiary of Jentayu Sustainables (KLSE:JSB), has received approval from the Energy Commission of Sabah to extend the financial close date and scheduled commercial operation date for its 162-megawatt Oriole Hydro Project.
The commission, in a letter dated Sept. 22, approved extending the financial close date to June 30, 2027, from Oct. 31. The scheduled commercial operation date has also been pushed to Dec. 31, 2030, from April 30, 2030.
Oriole Hydro Project is a run-of-river hydroelectric power plant located in the Hulu Sungai Padas area of the Sipitang Forest Reserve in Sabah.