Eurowind Energy Romania, a unit of Denmark's Eurowind Energy, has secured technical connection approvals for 2,307.4 MW of renewable energy capacity across seven wind, solar and battery storage projects, the company said in a statement.
The approvals, obtained in June, cover projects in Constanta, Prahova, Botosani, Braila and Galati counties. They include a 900 MW wind project in Albesti, a 49 MW photovoltaic and battery-storage project in Manesti, and a 1,188 MW wind project in Botosani County.
The remaining projects are wind farms in Stancuta (49.6 MW), Liesti (49.6 MW), Slobozia Conachi (49.6 MW) and Pechea (21.6 MW).
The approvals are a key step toward connecting the projects to Romania's power grid. Eurowind said the projects are scheduled for connection after 2030, subject to grid upgrades and the timely issuance of construction permits.
The company has a development pipeline of about 7.5 GW in Romania and has begun work on the Frumusita and Vector wind farms in Galati County, as well as the Pecineaga Nord-Est project in Constanta County, totaling 138 MW.
The Botosani project, the largest in the newly approved portfolio, is planned as nine wind farms built in phases, with construction expected to begin around 2031. The project is intended to support Romania's energy security and its potential role as a regional renewable-power exporter.
Eurowind Energy currently has 184 MW of capacity operating in Romania, including 60 MW of battery storage at Teius.