Eni (E) said Wednesday it generated first industrial electricity from the 120-megawatt gas power plant at the 247-MW Mangystau Hybrid Power Plant in Kazakhstan.
The company said the project, developed with KazMunayGas and Eni subsidiary Plenitude, is Kazakhstan's first large-scale hybrid power plant, combining solar, gas and planned wind generation.
Eni said the project's 50-MW solar plant began operating in September 2025, while the gas plant is expected to be fully commissioned in Q3.
A 77-MW wind farm is scheduled to begin operations in 2027, completing the hybrid facility, it added.