Edison International (EIX) reported Q2 earnings Thursday, highlighting continued progress on wildfire mitigation, grid hardening and its capital investment program.
Southern California Edison has completed over 14,760 circuit miles of grid hardening, representing about 90% of its distribution system in high fire risk areas.
The utility plans to complete roughly 970 additional circuit miles through 2028.
The company expects to invest $38 billion to $41 billion between 2026 and 2030 to strengthen its regulated electric transmission and distribution system.
The forecast through 2030 includes California Independent System Operator-awarded Federal Energy Regulatory Commission transmission projects with an additional $2 billion of such projects identified beyond 2030.
The forecast also includes investments approved under Southern California Edison's 2025 General Rate Case, about half of its planned $3.1 billion advanced metering infrastructure program and its planned 2029 General Rate Case request.
Beyond 2030, Edison International sees additional investment opportunities through its planned 2029 General Rate Case and the remaining half of its planned $3.1 billion advanced metering infrastructure program in 2031-2033.