Cheniere Energy (LNG) on Thursday reported Q2 2026 export volumes rose 22% to 672 trillion British thermal units from 550 TBtu in the same quarter in 2025. For the first half, export volumes rose 17% to 1,360 TBtu over 1,158 TBtu in the same period a year prior.
The US LNG exporter shipped 184 cargoes during the second quarter ended June 30, up from 154 cargoes a year earlier. For the first six months of 2026, cargoes increased to 371 from 322 in the prior-year period.
Cheniere said it raised the lower end of its 2026 production forecast, tightening its expected output range to 53 million to 54 million tonnes, compared with its previous guidance of 52 million to 54 million tonnes.
The company said it achieved substantial completion of Midscale Train 6 at its Corpus Christi Liquefaction Stage 3 project in June, following the completion of Midscale Trains 1 through 4 in 2025 and Midscale Train 5 in March 2026. Cheniere added that first LNG production from Midscale Train 7 is expected imminently.
Also in June, the Federal Energy Regulatory Commission authorized an increase in LNG production capacity for the CCL Stage 3 project and the CCL Midscale Trains 8 and 9 project by a combined approximately 5 million tonnes per annum.
Separately, in May, Sabine Pass Liquefaction Stage V LLC, a subsidiary of Cheniere Energy Partners, signed a lump-sum turnkey engineering, procurement and construction contract with Bechtel Energy for the first phase of the Sabine Pass LNG expansion project. The company has authorized Bechtel to begin early engineering and procurement activities under a limited notice to proceed.
Chief Executive Jack Fusco said the quarter was marked by the completion of Midscale Train 6 and continued progress toward a final investment decision for Phase 1 of the Sabine Pass expansion project.