Bannerman Energy Says Bulk Earthworks Contract Around 92% Complete at Namibia Uranium Project
Bannerman Energy (ASX:BMN) said the bulk earthworks contract is advancing in line with schedule, with around 92% completed at its Etango uranium project in Namibia, according to a Monday Australian bourse filing.The contractor workforce on site now consists of over 560 personnel. The production of heap leach drainage aggregate continues to deliver on-spec material, with around 29% of the total requirement completed.The civil and mechanical design for the dry plant is around 94% completed.Its shares rose 2% in recent trading on Monday.