TotalEnergies SE (TTE) and Eni (E) have reached a final investment decision to develop the Cronos gas field in offshore Block 6 in Cyprus, the country's first-ever commercial gas development, Total said on Tuesday.
Production is scheduled to start up in 2028, with a targeted plateau production rate of 500 million cubic feet per day equivalent to roughly 2.8 million tons of LNG per year, it said.
Located about 185 kilometers southwest of the Cypriot coast, the deep-water project will utilize four subsea wells to transport gas via a subsea pipeline to Egypt, where it will be liquefied at the Damietta LNG terminal utilizing Zohr field infrastructure synergies before export to Europe, it said.
TotalEnergies will market 50% of the output, amounting to 1.4 Mtpa, as part of its strategy to expand its global LNG portfolio to 60 Mtpa by 2030.
Following a Host Government Agreement signed in February 2025, commercial frameworks have been secured to establish this new Eastern Mediterranean energy corridor, which aims to enhance European energy security and unlock future resource developments across Block 6, the statement said.