NRW Holdings' (ASX:NWH) wholly owned subsidiary Fredon secured an around AU$115 million first-stage design and construct mechanical contract for Stack Data Centers' MEL03 hyperscale data center in Melbourne, according to a Thursday filing with the Australian bourse.
The off-site fabrication works are scheduled to run from September to March 2028 and will support the delivery of mechanical systems for 432 megawatts of the 864-megawatt campus, per the filing.
The award is part of a broader about AU$300 million package of works for which Fredon has been named the preferred contractor, with completion expected in 2028, the filing added.