Matsa Resources (ASX:MAT) began Campaign 3 for the processing of gold ore from its Devon Pit Gold Mine in Western Australia on schedule, with gold ore stockpiled at FMR's Greenfield processing plant and a 13-day processing window available, according to a Friday Australian bourse filing.
The company said Campaign 3 is six days shorter than Campaign 2 due to FMR operational requirements, and that mining is on track to equal or exceed Campaign 2 ore grade.
Processing for Campaign 4 is planned for late July 2026, per the filing.