Utility firm Electricite de France extended a maintenance outage at its Gravelines 5 nuclear reactor until Jan. 25, adding seven weeks to the planned schedule and cutting power capacity during peak winter heating demand, Bloomberg reported on Thursday.
Preventative checks reportedly detected potential stress corrosion on primary loop piping during a routine overhaul, prompting additional testing to determine if replacements are required.
EDF expanded its fleet-wide pipe inspection protocol following severe stress corrosion issues in 2022 and 2023.
EDF did not immediately respond to a request for comment from.
(Market Chatter news is derived from conversations with market professionals globally. This information is believed to be from reliable sources but may include rumor and speculation. Accuracy is not guaranteed.)