Jacobs Solutions (J) will support EnergyPathways' regulatory and planning work for its MESH energy storage project, targeting operations by 2031, the company said Tuesday.
Jacobs will lead the planning and development consent order strategy, including environmental planning, technical coordination and stakeholder engagement under the UK's Nationally Significant Infrastructure Project process.
MESH will operate in the Irish Sea, with onshore infrastructure connecting to Barrow-in-Furness, and could become one of the UK's largest integrated energy storage projects at 300 megawatts and 55 gigawatt-hours.
The project will combine compressed air energy storage with natural gas and hydrogen storage to balance renewable generation and provide more than 190 hours of storage.
Jacobs will also help EnergyPathways apply to Ofgem's upcoming long-duration electricity storage cap-and-floor scheme, while managing environmental and technical work and supporting the grid connection application.
Jacobs will engage local councils and regional government, align statutory consents and technical studies with the project schedule, and assess planning and legislative changes to identify risks and streamline regulatory delivery.
"Our extensive experience delivering complex infrastructure projects through the Development Consent Order process will support EnergyPathways in navigating planning and regulatory requirements while maintaining project momentum," said Richard Sanderson, Jacobs executive vice president.
Price: $144.83, Change: $-1.41, Percent Change: -0.96%