The Federal Energy Regulatory Commission approved Cheniere Energy's (LNG) request to introduce feed gas to the warm end of Midscale Train 7 at its Corpus Christi Stage 3 project, according to a Tuesday letter.
FERC approved Cheniere's July 27 request after reviewing inspections and compliance filings, saying the request meets the conditions of its Nov. 22, 2019 authorization order.
FERC said the approval does not authorize Cheniere to construct, commission, or introduce hazardous fluids into other Corpus Christi Stage 3 facilities.
The agency will continue reviewing and inspecting the liquefied natural gas terminal, with additional recommendations possible before issuing further authorizations, FERC said.
The approval brings the largest US liquefied natural gas exporter closer to starting production from the seventh and final train at Corpus Christi Stage 3, which will add over 10 million metric tons of liquefied natural gas capacity, according to a report by Reuters.
Price: $251.56, Change: $-4.32, Percent Change: -1.69%