Catalyst Metals (ASX:CYL) completed a study to increase throughput at the Plutonic processing plant in Western Australia, according to a Tuesday filing with the Australian bourse.
The study, which contemplated increases to between 2.5 million tonnes and 3 million tonnes per year of processing capacity from the current 2 million tonnes per year, indicated a potential low-capital pathway to raise capacity by refurbishing a second processing circuit, the filing said.
A decision to increase processing capacity hinges on the success of ongoing exploration in the Plutonic Belt, per the filing.