Brightstar Resources (ASX:BTR) said its board approved a final investment decision for its Goldfields project in Western Australia, which is fully funded to achieve first gold in the June 2027 quarter, according to a Tuesday filing with the Australian bourse.
The project is expected to deliver average gold production of about 75,000 ounces per annum over an initial mine life of six years, per the filing.
Following the final investment decision, Brightstar is starting full-scale construction activities at the 1.5 million tonnes per annum Laverton processing plant.