-- Dynacor Group (DNG.TO) said Wednesday that its expansion projects in Senegal and Ecuador remain on track to process first ore in 2026.
In Senegal, Dynacor said the 50-tonne-per-day pilot plant in Kedougou continues to advance on schedule. Mechanical installation of major equipment will be launched shortly, and all required permits are in place to begin commissioning in the second quarter.
In Ecuador, Dynacor said it continues to advance integration and upgrade of the Svetlana processing plant, with gold production expected to begin in the fourth quarter.
Meanwhile, Dynacor said its board concluded that the practices of its Peruvian subsidiary that had been under review are currently consistent with the company's values.
The review is part of a reorganization of Dynacor's Peruvian business.