US Coal Phase-Out Slows in 2025 With Just 2.6 GW Retired, Plans Shift Ahead, EIA Says

-- US coal-fired capacity retirements dropped to 2.6 gigawatts in 2025, the lowest level since 2010, the US Energy Information Administration said Monday.

Operators had initially scheduled about 8.5 GW of closures for 2025, but nearly 4.8 GW were pushed to later years while roughly 1.1 GW of retirements were scrapped, the report said.

Plans to shut 1.2 GW of coal capacity slated for 2027 were withdrawn, while another facility postponed its expected 2026 closure timeline to 2029, according to the EIA.

Coal capacity closures have eased significantly from earlier years, with 2022 seeing 13.7 gigawatts, roughly 6.5% of the fleet, shut down, compared with much lower levels recorded in 2025.

Only four facilities retired coal units in 2025, including sites in Delaware, Arizona, Utah, and Iowa, together accounting for about 2.6 GW or roughly 1.5% of total capacity, the agency said.

The Intermountain Power Project in Utah represented the largest closure, with 1,800 MW retired, though part of its capacity was replaced by a 1,017 MW natural gas-fired plant at the same site, the report said.

Federal intervention also slowed retirements, as the US Department of Energy issued emergency orders requiring several coal plants to remain available to support grid reliability, the agency said.

These directives covered facilities across multiple states, including Michigan, Washington, Indiana, and Colorado, with a combined capacity exceeding 3 GW, according to the EIA.

Most of the affected plants have since deferred their retirement timelines from 2025 into early or mid-2026, according to the EIA.

Additional delays came from three other plants totaling about 2.2 GW, where operators opted to postpone closures originally scheduled for 2025, the report added.

In one case, Transalta Centralia Unit 2 in Washington is now set to be converted into a natural gas-fired facility, with the transition currently targeted for completion by 2028.

Looking ahead, about 6.4 GW of coal capacity, or nearly 4% of the fleet, is expected to retire in 2026, although these projections remain subject to policy and market developments, the EIA said.

相关文章

Asia

Euroz Hartleys表示,西非资源产量将在未来几个季度增长。

Euroz Hartleys周四在一份报告中指出,西非资源公司(ASX:WAF)的黄金产量预计将在未来几个季度有所增长,这主要得益于Sanbrado和Kiaka矿井地下矿石品位的提升。 该公司公布的第一季度集团黄金产量为107,700盎司,运营现金流为4.4亿澳元,使其现金和黄金储备余额达到创纪录的10.6亿澳元。 该公司还维持了2026年43万至49万盎司的产量预期,与Euroz Hartleys此前预测的470,500盎司一致。 这家投资公司认为,鉴于西非资源公司的产量和现金流状况,其股价被“严重低估”,尤其是在布基纳法索政府以1.75亿澳元收购其Kiaka矿25%的股份之后,这一举措消除了一个主要的不确定因素。 当前金价上涨以及公司强劲的现金流预计将支持其提前偿还债务和持续资本回报,近期派发的每股0.15澳元特别股息被视为众多股息中的第一个。 Euroz Hartleys重申对西非资源公司(West African Resources)的投机性买入评级,并将目标价从5.50澳元上调至5.55澳元。

$ASX:WAF
Asia

Vulcan Energy Resources公司称,其位于德国的锂化工厂正在建设中。

据周五提交给澳大利亚证券交易所的文件显示,Vulcan Energy Resources(ASX:VUL)宣布其位于法兰克福的锂化工工厂已开工建设。 该工厂将采用电解法将氯化锂转化为氢氧化锂一水合物(LHM)。该公司表示,一期工程的目标产能为每年2.4万吨LHM,足以满足约50万块电动汽车电池的需求。

$ASX:VUL
Asia

FleetPartners加快股息抵免时间表

FleetPartners Group(ASX:FPR)在完成2025财年税务申报后更新了股息展望。根据周五提交给澳大利亚证券交易所的文件,该公司预计未来的股息,包括任何上半年中期派息,都将比原计划的9月份提前全部获得税收抵免。 该公司还在文件中确认,将于5月7日向澳大利亚证券交易所发布其2025财年上半年财务业绩。

$ASX:FPR