FINWIRES · TerminalLIVE
FINWIRES

Gap Widening Between Study-Stage Renewable Projects, Connected Grid Capacity in Japan, IEEFA Says

By

Despite an expanding line-up of renewable energy projects, the conversion from application to physical grid remains weak in Japan, according to an analysis by the Institute for Energy Economics and Financial Analysis published Friday.

Only about 87 gigawatts have been connected to the grid from about 317 GW of wind, solar, and storage capacity under study as of December last year, the study said, citing the country's grid application data.

With a connected capacity about 2.3 times the volume at the study stage, solar energy has exhibited the highest realization in Japan. However, transmission-dependent technologies such as offshore wind and battery storage have displayed significantly weaker conversion rates.

Onshore wind, offshore wind, and battery storage have conversion rates of around 14%, below 1%, and 0.35%, respectively, IEEFA said.

According to IEEFA, the challenges around Japan's renewable energy bottleneck stem more from institutional design, rather than ambition or resource constraints

"The widening gap between study-stage projects and connected capacity suggests that Japan's renewable energy bottleneck is fundamentally institutional in nature," IEEFA analysts said.

IEEFA added that without reforms that enhance cost transparency, project prioritization, and transmission coordination, "capacity is likely to continue accumulating in the queue without translating into large-scale transformation of the power system."

The country's grid connection bottleneck results from three structural issues in its interconnection framework: cost allocation, queue design, and geographic transmission constraints, IEEFA said.

Japan's framework uses the "causer pays" system under which the cost risks associated with upgrades are transferred to the developers, increasing their financial risk.

At the same time, weak controls in the project queue allow speculative projects to compete with ready-to-build projects for limited grid capacity, while geographic transmission constraints are causing bottlenecks between power-producing regions and major demand centers, it said.

"If left unchanged, this structure could continue to slow renewable energy deployment, not because projects are lacking, but because the interconnection framework constrains the conversion of applications into operational capacity," IEEFA analysts added.

Related Articles

Commodities

EV Charging Infrastructure Remains Top Barrier to Adoption, JD Power Says

Charging infrastructure remains the biggest obstacle to electric vehicle adoption in the US, even as consumer interest in EVs continues to rise, the 2026 US Electric Vehicle Consideration Study released Friday by JD Power said.The study found that charging station availability was the leading reason shoppers rejected EVs, cited by 46% of respondents. Concerns about charging time ranked second at 44%. While both concerns improved from a year earlier, JD Power said charging access remains a critical barrier for many buyers."While concerns around driving range and public charging are easing, consideration among shoppers who can't charge at home or work has barely moved," said Brent Gruber, executive director of OEM and EV solutions at JD Power. "Without meaningful progress in these areas, a large share of would-be EV buyers will remain out of reach."The study showed EV consideration remained stagnant among residents of apartments, condominiums, and townhouses, where home charging access is often limited. Only 18% of apartment residents and 17% of condo or townhouse residents said they were "very likely" to consider purchasing an EV, down from a year earlier.JD Power said many consumers who remain hesitant about EVs have high expectations for charging convenience. Among shoppers who said they were "very unlikely" to consider an EV, 43% said charging availability would need to match that of gas stations, while nearly three-quarters said they would require at least 500 miles of driving range before considering an EV purchase.Gruber said public fast chargers are often more accessible than consumers realize, but awareness among drivers who do not already own EVs remains low.Despite infrastructure concerns, overall EV interest increased in April as gasoline prices climbed. The share of shoppers who said they were "very likely" to consider an EV rose to 26% in April, up three percentage points from March, while the percentage who were "very unlikely" to consider one fell to 18%.The study surveyed 8,154 consumers planning to buy or lease a new vehicle within the next 12 months.

Commodities

US Natural Gas Update: Futures Rise Nearly 2% on Bullish Storage Build, Drop in Output

US natural gas futures were up on Friday, after the weekly storage report fell short of forecasts, alongside the continued slide in output.Both Henry Hub front-month futures and the continuous contract rose by 1.76% to $2.945 per million British thermal units.The benchmark was set to end the week up by 6.70%, according to data from TradingEconomics.On Thursday, the US Energy Information Administration reported a net injection of 85 billion cubic feet into storage for the week ended May 8, which was above the prior week's 63 Bcf, but fell marginally short of forecasts at 86 Bcf, according to data compiled by Investing.com.Natural gas output continued to slide this week, to 106 Bcf per day on Wednesday, down from 107.7 Bcf/d last week, according to NRG Energy.LNG feedgas flows to export facilities remained low at 17.51 Bcf on Thursday, compared to the 30-day moving average of 18.75 Bcf, according to the Bloomberg LNG Feedgas Model. This was attributed to major LNG export facilities undergoing seasonal maintenance.Weather forecasts have turned bullish, with most parts of the US expected to see above-normal temperatures from May 22 to May 28, according to the National Weather Service. This is expected to increase gas demand for cooling.According to Gary Cunningham of Tradition Energy, LNG prices should remain "range bound" and under $3 per MMBtu because there isn't enough fundamental support to keep prices elevated.

Commodities

Grupo Cox Closes $4.2-Billion Iberdrola Mexico Asset Acquisition

Grupo Cox, a Spanish multinational water and energy company, has closed its $4.2 billion acquisition of Iberdrola's Mexico assets, adviser DLA Piper said Thursday.The acquisition includes 2.6 gigawatts of installed operating capacity, 12 GW of renewable projects pipeline, and a private power supplier in Mexico with 20 terawatt-hours of commercialized capacity and more than 500 large corporate customers.Cox funded the transaction through a $2.65 billion in bank financing, capital outlay, and additional funds from institutional investors, according to the statement.