-- G Mining Ventures (GMIN.TO) 周二发布了其全资拥有的圭亚那 Oko West 金矿项目截至 2026 年第一季度的最新进展。该公司表示,该项目持续按计划和预算推进,预计将于 2027 年下半年实现首次黄金浇铸,并于 2028 年 1 月开始商业化生产。 该公司表示,自 2025 年 10 月启动开发活动以来,在工程、采购、场地基础设施和选矿厂建设方面取得了显著进展,同时提高了成本可见性和执行确定性。安全绩效“依然强劲”,迄今为止仅记录到一起工时损失事故,总可记录事故频率为 0.37。 该公司还报告称,根据已挣值计算,项目整体进度已达到 19.7%,建设工作正按计划推进。迄今为止已支出约 2.92 亿美元,承诺投资额为 5.25 亿美元。 该项目仍保持在预算范围内。详细的工程和采购工作已完成约 80%。 该公司补充道,Oko West 2026 年和 2027 年的总资本支出预期维持不变,分别为 5.14 亿美元至 5.68 亿美元和 2.17 亿美元至 2.4 亿美元。基础设施详细设计计划于 2026 年第二季度完成,工艺装置的详细工程设计已完成 70%。 周一,该公司股票在多伦多证券交易所收盘下跌 0.7%,报 47 美元。
Related Articles
Ethos Technologies Launches Native ChatGPT App for Life Insurance Estimates
Ethos Technologies (LIFE) has launched a native ChatGPT app to provide dedicated AI assistance for users interested in life insurance.Users will be able to receive a personalized monthly term life insurance estimate after answering five simple questions within the chatbot, according to a statement.Price: $19.90, Change: $+0.44, Percent Change: +2.26%
GE Vernova, Blue Energy Collaborating on Nuclear-Natural Gas Power Plant
GE Vernova (GEV) and Blue Energy are planning to develop a 2.5 gigawatt power facility in Texas that will combine nuclear and natural gas, the companies said Tuesday.The plan incorporates GE Vernova Hitachi Nuclear Energy's small modular reactor and two GE Vernova 7HA.02 gas turbines, the companies said. A final investment decision is expected in 2027 and the gas turbines are expected to be delivered in 2029.Blue Energy could begin preliminary site work on the project this year and submit an application to the US Nuclear Regulatory Commission for a construction permit in 2027, the companies said.Financial terms were not disclosed.Price: $1104.33, Change: $+30.38, Percent Change: +2.83%
American Electric Power Q1 Energy Delivery Mixed
US utility American Electric Power (AEP) on Tuesday reported its Q1 results, showing a decline over the year in energy delivered by vertically integrated utilities, and a rise in energy delivered by transmission and distribution utilities.For the quarter ended March 31, the vertically integrated utilities segment delivered 27.777 terawatt-hours of energy, down from 28.725 TWh in the prior year, largely due to a 26% drop in wholesale volumes.On the other hand, the transmission and distribution utilities segment delivered 26.990 TWh of energy in Q1, up from 24.194 TWh in the previous year, driven by a 33% rise in retail commercial sales.The company said its incremental load is expected to expand to 63 gigawatts by 2030, following new load agreements, totaling 7 GW, signed in Q1.American Electric also received a new contract award for 765-kilovolt transmission projects across SPP and PJM service areas.To support growth, the firm said it raised its five-year capital plan to $78 billion from $72 billion, improving the compound annual growth rate of operating earnings by at least 9% through 2030.Price: $137.14, Change: $+2.48, Percent Change: +1.84%